What adjudication is
Adjudication is the engine room of the security of payment regime. It is a fast, statutory dispute process in which an independent adjudicator decides how much is payable on a payment claim s 17, Building and Construction Industry Security of Payment Act 1999 (NSW) (as of 8 July 2026). It is not a court case and it does not settle your rights forever — it is designed to get cash to the claimant quickly and keep it there while any final legal dispute is fought out separately. In practice, for most unpaid subbies and contractors, adjudication is the remedy.
When you can adjudicate
You have a right to apply for adjudication when s 17, Building and Construction Industry Security of Payment Act 1999 (NSW) (as of 8 July 2026):
- the payment schedule states a scheduled amount less than the amount you claimed;
- the respondent served a schedule but failed to pay the scheduled amount by the due date; or
- the respondent served no payment schedule and did not pay the claim by the due date.
Each trigger has its own statutory window to apply, and the windows are short. Where no schedule was served, the Act generally requires you to first notify the respondent of your intention to adjudicate and give them a last short chance to provide a schedule s 17, Building and Construction Industry Security of Payment Act 1999 (NSW) (as of 8 July 2026). Miss the window and the right lapses — see the payment-schedules guide for how the schedule outcome sets which window applies.
On the timeframes: the application, response, and determination periods are set by the current Act, measured in business days, and some can be shortened by your contract. Any date that will drive a real step must be confirmed against the Act text with a construction lawyer. TODO: counsel-verify all adjudication day-counts and notice requirements before go-live.
What an application needs
The adjudication application must be in writing, made within the statutory time, and lodged with an authorised nominating authority (ANA) s 17, Building and Construction Industry Security of Payment Act 1999 (NSW) (as of 8 July 2026). It should identify the payment claim and any payment schedule it responds to, be accompanied by the application fee, and may attach whatever submissions and supporting evidence you want the adjudicator to consider s 17, Building and Construction Industry Security of Payment Act 1999 (NSW) (as of 8 July 2026). The ANA then refers the application to an eligible adjudicator, who decides whether to accept it s 18, Building and Construction Industry Security of Payment Act 1999 (NSW) (as of 8 July 2026).
Put your whole case in the application. Because the respondent is confined to the reasons already stated in its payment schedule s 20, Building and Construction Industry Security of Payment Act 1999 (NSW) (as of 8 July 2026), you are arguing against a fixed target — do not hold material back.
The steps, in order
- Confirm you can adjudicate. Check you have a trigger: the payment schedule is for less than you claimed, the scheduled amount was not paid by the due date, or no schedule was served and the claim was not paid. Each has its own statutory window to apply.
- Give any required notice. Where no payment schedule was served, notify the respondent of your intention to apply for adjudication and give them the short statutory opportunity to provide a schedule before you proceed.
- Prepare the adjudication application. Put the application in writing, identify the payment claim and any payment schedule, attach your supporting submissions and evidence, and include the application fee. Make your case fully here — the respondent is limited to the reasons already in its schedule.
- Lodge with an authorised nominating authority. Lodge the application within the statutory window with an authorised nominating authority (ANA), which refers it to an eligible adjudicator who decides whether to accept the adjudication.
- Respondent lodges its response. A respondent that served a payment schedule may lodge an adjudication response within the statutory time. It cannot include reasons for withholding payment that were not in the schedule.
- Adjudicator determines the amount. The adjudicator determines the amount payable, the date it became payable, and the interest rate, within the statutory period. The determination is enforceable — you can obtain an adjudication certificate and file it as a judgment debt if it is not paid.
The respondent’s response
A respondent may lodge an adjudication response, but only if it served a payment schedule in the first place, and only within the statutory time s 20, Building and Construction Industry Security of Payment Act 1999 (NSW) (as of 8 July 2026). Critically, the response cannot include reasons for withholding payment that were not in the schedule s 20, Building and Construction Industry Security of Payment Act 1999 (NSW) (as of 8 July 2026). A respondent who stayed silent, or wrote a thin schedule, cannot fix that now — the reasons lock is the claimant’s biggest structural advantage in the whole regime.
What the adjudicator decides
The adjudicator determines the adjudicated amount payable, the date it became or becomes payable, and the rate of interest s 22, Building and Construction Industry Security of Payment Act 1999 (NSW) (as of 8 July 2026). In reaching that, they may consider only a defined list — the Act, the construction contract, the payment claim and schedule together with their submissions, and the results of any inspection s 22, Building and Construction Industry Security of Payment Act 1999 (NSW) (as of 8 July 2026). The determination must be made within the statutory period s 21, Building and Construction Industry Security of Payment Act 1999 (NSW) (as of 8 July 2026).
If the respondent does not pay the adjudicated amount by the due date, you can obtain an adjudication certificate and file it in court as a judgment debt s 24, Building and Construction Industry Security of Payment Act 1999 (NSW) (as of 8 July 2026)s 25, Building and Construction Industry Security of Payment Act 1999 (NSW) (as of 8 July 2026). An unpaid claimant may also have a right to suspend work s 27, Building and Construction Industry Security of Payment Act 1999 (NSW) (as of 8 July 2026). That enforceability — a court-grade result in weeks — is why adjudication is the wedge the whole regime turns on. The Security of Payment hub links the adjudication checklist and timeframe calculator as they ship.